A payment claim arrives from the formwork subcontractor with a signed subcontractor's statement. The certificate of currency (the insurer's confirmation that a policy is in force) attached to it ran out at the end of June. The register says "current" because nobody updated the row when the last renewal reminder went unanswered. If you are a principal contractor in NSW, that gap matters: the statement is the document that relieves you of liability for the subcontractor's workers compensation premiums, and it is meant to come with the relevant certificate.

Most registers fail for the same reason. They track one expiry date per document, when the real question is whether a period of cover matches a period of work. This guide sets out a register built around periods, the rules that should run against it, and which parts software can do without a person.

In short

  • Track periods, not dates. A certificate covers a period; a statement covers a period of work; a payment claim covers a period. The check is whether they overlap correctly.
  • In NSW, the subcontractor's statement and its certificate travel together. The Revenue NSW form says the statement must be accompanied by the relevant certificate of currency where required (S1).
  • Seven rules catch most gaps. Expiry, coverage of the contract period, name and ABN (Australian Business Number) match, limit against the contract, continuous statement periods, missing signature or date, and licence status.
  • Software reads and checks; people judge. Whether cover is adequate for the work, and whether to hold a payment, stays with your team.
  • Last checked: 9 October 2026. This is commercial guidance, not legal advice. Confirm your obligations for a specific contract with SIRA (the State Insurance Regulatory Authority), Revenue NSW or your lawyer.

The documents and what each one proves

Document What it is evidence of The date logic that matters
Workers compensation certificate of currency The insurer confirms a policy is in force for a stated period Policy period must cover the work and the payment claim period
NSW subcontractor's statement The subcontractor declares premiums, payroll tax and remuneration have been paid for a stated period of work, linked to a payment claim (S1) Statement period must match the claim; sequential statements should give continuous coverage (S1)
Public liability certificate of currency Cover of a stated limit for a stated period Limit must meet the contract; period must cover the work
Contractor licence Holder is licensed for a category of work Status and expiry on the public register at the time of work (S2)
UK employers' liability certificate Employer holds EL cover of at least GBP 5 million from an authorised insurer (S3) Policy period; insurer authorised (FCA register)

Three facts about the NSW statement shape any tracker (all from the Revenue NSW form, S1):

  1. It is prepared for section 175B of the Workers Compensation Act 1987, Schedule 2 Part 5 of the Payroll Tax Act 2007 and section 127 of the Industrial Relations Act 1996. Completed in accordance with those provisions, it relieves the principal contractor of liability for the subcontractor's premiums, payroll tax and remuneration.
  2. It states the period of work it applies to and the payment claim it relates to, and records the date of the attached certificate of currency.
  3. The principal contractor must keep a copy for the periods in the legislation, currently up to seven years. Giving a statement known to be false is an offence.

Other states and territories have their own arrangements. They were not checked for this guide (UNKNOWN); confirm with the relevant regulator before applying the rules below outside NSW.

The register: fields that make the rules possible

A register that can be checked automatically needs these fields for every document. The column most registers lack is the period start.

Field Why it is needed
Holder legal name and ABN (or UK company number) Match to the subcontract; catch a certificate in a related company's name
Document type Selects which rules apply
Issuer (insurer or licensing body) and policy or licence number Trace and verify
Cover type and limit Compare with the contract requirement
Period start and period end The basis of every date rule
Linked contract and, for statements, the linked payment claim Ties evidence to money
Source file, page and the exact text each value came from A reviewer can check any value in one click
Extracted by, confirmed by, date confirmed Who stands behind each record

Seven rules a tracker should apply

Rule Trigger Severity
R1 Expiry warning Period end within 60 days, then 30 days Reminder drafted for approval
R2 Expired Period end before today, and the subcontractor is active Block: shown on the exceptions list until resolved
R3 Period does not cover the claim Payment claim or statement period falls outside the certificate period Block
R4 Name or ABN mismatch Holder on the certificate differs from the subcontract party Block
R5 Limit below contract Stated limit is lower than the contract requirement Block
R6 Statement gap Sequential statements leave days uncovered Warn
R7 Incomplete statement Unsigned, undated, no certificate date recorded, or the "no workers" box ticked while the subcontract involves labour Block

Licence status (from the public register) is a scheduled manual check: the system reminds, a person searches the register and records the result. The Service NSW licence check can be searched by licensee name, licence number, licence type, ABN, ACN or location (S2).

A worked register

A head contractor in NSW, three active subcontractors, register run on 9 October 2026. Contracts require public liability of at least AUD 20 million.

Subcontractor Document Period Limit What the rules find
Electrical sub Public liability certificate 1 Nov 2025 to 31 Oct 2026 AUD 10 million R1: expires in 22 days. R5: limit is half the contract requirement
Formwork sub Workers compensation certificate 1 Jul 2025 to 30 Jun 2026 n/a R2: expired 101 days ago
Formwork sub Subcontractor's statement Work 1 Sep 2026 to 30 Sep 2026, claim dated 2 Oct 2026, certificate dated 1 Jul 2025 n/a R3: the statement's work period is outside the certificate period. Claim held for review
Plumbing sub Licence Register searched 12 Aug 2026 n/a Next manual register check due (58 days since last search)

Day counts: 9 October to 31 October is 22 days. 30 June to 9 October is 101 days (0 + 31 + 31 + 30 + 9). 12 August to 9 October is 58 days (19 + 30 + 9).

What a date-only spreadsheet would show: the electrical sub "current", because 31 October is in the future; the formwork certificate "expired", but with nothing linking it to the statement attached to a live payment claim. The register above links the three facts that matter (the claim, the statement and the certificate) and blocks the claim until someone looks.

Who does what

You provide: the shared inbox or folder where certificates arrive, a list of active subcontracts with legal names, ABNs and required limits, and payment claim dates.

The system does: reads each certificate and statement, extracts holder, issuer, policy number, cover, limit and period with the exact source text, applies the seven rules, drafts renewal requests for the 60-day and 30-day warnings, and produces a weekly exceptions list.

The reviewer approves: every new record before it counts as evidence, every block, and every reminder before it is sent.

What is exported: the register (Excel or CSV) with source text and confirmation history, and the exceptions list.

What stays manual: judging whether a policy actually covers the work (exclusions, endorsements, the description of business), deciding worker or contractor status, licence register searches, and the decision to hold a payment or keep someone off site. Software can tell you that a document is missing or does not match. It cannot tell you what to do about it.

The UK version

The same register works for UK supply chains with different documents. Employers must hold employers' liability cover of at least GBP 5 million from an authorised insurer, display the certificate where employees can see it, and can be fined GBP 2,500 for every day without proper insurance and GBP 1,000 for failing to display it (S3). GOV.UK points to the FCA register to check that an insurer is authorised (S3). No general statutory duty for a client to check its contractors' insurance was found in the sources opened (UNKNOWN); in practice the requirement usually sits in the contract or a prequalification scheme, and the register enforces what the contract says.

Where the Supplier Document Tracker fits

The Supplier Document Tracker is a PhaseVane workflow built to the rules above: extraction with source text, deterministic date and limit checks, and a person confirming every record and every block. It is in development and not on sale. PhaseVane is looking for design partners, particularly NSW contractors holding statements and certificates for 20 or more subcontractors, to test it on real documents. The controls are described in the review controls behind document extraction. If you are deciding between this and other workflows, score it against your other workflows.

Book a 20-minute workflow call. Bring your current register and three recent certificates. You leave with a note on which checks can be automated and which must stay with your compliance team. Book a workflow call

Want to test it on your own documents? Join the design-partner list.

Sources

Checked 9 October 2026.

Bring your current register and three recent certificates. You leave with a note on which checks can be automated and which must stay with your compliance team.

Book a 20-Minute Workflow Call

Or see Quote Desk.

Related Research

See all research notes

Topic: Procurement Automation

  1. Cost Driver Monitoring: Is This Supplier Price Increase Justified?

    Map each supplier cost element to a free public index, track it monthly, and test a price increase claim against the weighted move. Worked example.

    Procurement Automation
    Read More
  2. Freight Quote Comparison Automation: Can It Keep the Detail?

    How automated intake turns forwarder quotes from email, PDF and Excel into one comparison without dropping surcharges, TBA lines or validity.

    Procurement Automation
    Read More
  3. Human Review in Procurement Automation: What Stops a Misread Value?

    Ten controls that stop a wrong extracted value reaching a purchase order: source text checks, code-only maths, blocking flags and an approval log.

    Procurement Automation
    Read More